Health Sciences Building on Main Campus
Architect: Lord Aeck Sargent
Construction Manager: Skanska
Project Manager: 35 North
Size: 80,000 square feet
Cost: $77 million
Funding: 2022 bond referendum
This new facility will be home to programs including Nursing, Surgical Technology, Anesthesia Technology, Respiratory Therapy, Clinical Research, and Occupational Therapy.
- 4 classrooms and 2 computer labs
- 21 allied health labs & simulations
- 1,600 ft2 of student collaboration areas​
- 14,000 ft2 of academic support areas​
- 1,500 ft2 of building support
Updates
- Building 8 Demolition completed Friday, July 11, 2025.
- Temporary pedestrian walkway construction begun July 14, 2025 and is scheduled for completion by August 8, 2025. Once finished, the remaining perimeter fencing around the construction zones will be installed.
- Perimeter fencing for the new Health Sciences Building installed July 21, 2025, and Parking Lot F is now closed.
- Perimeter fencing for the new Life Sciences Building installed July 28, 2025, and Parking Lot D is now closed.